PRAGUE, Nov 15 (Reuters) - The second unit at Czech Temelin nuclear power station will reconnect to the electricity grid in the coming days, an official from plant owner CEZ <CEZPsp.PR> said on Wednesday.

Temelin's Unit 2 had been shut for a regular fuel exchange, but last week the plant's spokesman said the reactor was getting ready for re-launch and the State Authority for Nuclear Safety (SUJB) had given its permission for the plant to be reconnected.

Temelin is the biggest asset of state-owned utility CEZ. ((Reporting by Jan Korselt, writing by Alan Crosby; prague.newsroom@reuters.com; Reuters Messaging: alan.crosby.reuters.com@reuters.net; +420 224 190 477))